This is the project of boy Modal school ( Real Quantity Estimation of building ) so after reading this article you will be able to know Estimation for full building project.
P.C.C in foundation footing
3’0″x 3’0″ x 0.5 x 9 Nos = 40.5 cft
Material required
Cement = 7 bags
sand = 27 cft
Aggregate = 35 cft
R.C.C for column up to 5 feet height
9″x 9″x 5’0″x 9 nos = 25.31 cft
Material required
cement = 5 bags
sand = 17 cft
Aggregate = 22 cft
R.C.C for Column Footing
3’0″ x 3’0″x 0.75 x 9 nos
Material Required
cement = 10 bags
sand = 40 cft
3/4 Aggregate = 51 cft
Tie Beams all Round and Inside
22’3″ x 9″ x 9″ x 3 nos = 37.54 cft
21’0″ x 3 Nos x 9″ x 9″ = 35.4375
Total = 72.95 cft
Material Required
Cement = 14 nos
Sand = 40 cft
3/4 Aggregate = 52 cft
Volume of 2 walls and each wall thickness is 9 inch
22’3″ x 9″ x 9’0″ x 2 = 310 .54 cft
21’0″ x 9″ x 9’0″ x 3 = 425.25 cft
Material required
Cement = 58 bags
Sand = 478 cft
Brick = 18,000 Nos
Inner wall plastering
23’0″ x 9’0″ x 2 = 414 cft
21’0″ x 9’0″ x 4 = 756 cft
Total = 1170 cft
Material required
Cement = 47 Nos
Sand = 760 cft
External wall plastering
23’0″ x 9’0″ x 2 = 414 cft
21’0″ X 9’0″ x 2 = 378 cft
Total = 792 Cft
Material required
Cement = 32 Nos
sand = 514 Cft
Quantity of R.C.C roof of 1:2:4
23’0″ x 21’0″ x 0.375 = 182 cft
Material required
cement = 39 nos
sand = 313 cft
3/4 Aggregate = 410 cft
Estimation for additional works
P.C.C in foundation
3’0″ x 3’0″x 0.5x 12 Nos = 54 cft
Material required
Cement = 5 Nos
Sand = 36 cft
1 1/2 Aggregate = 46 cft
R.C.C Column up to 5 feet Height
9″ x 9″ x 5’0″ x 12 Nos = 33.75 Cft
Material required
Cement = 8 Nos
Sand = 22 Cft
3/4 Aggregate = 29 Cft
R.C.C for column footing
3’0″ x 3’0″x0.75 x 12 Nos = 81 cft
Materials required
Cement = 14 Nos
Sand = 53 Cft
3/4 Aggregate = 69 Cft
Tie Beams all round and inside
8’0″ x 9″ x 9″ x 6 = 27 cft
21’0″ x 9″ x 9″ x 2 = 23.625 Cft
20’9″ x 9″ x 9″ x 2 = 23.34375 cft
9’6″ x 9″ x 9″ x 2 = 10.6875 Cft
Total = 84.65625 Cft
Material Required
Cement = 19 Nos
Sand = 56 Cft
3/4 Aggregate = 72 Cft
Quantity for bricks all wall thickness is 9 inch
8’9″ x 9″ x 9’0″ x 4 = 236.25 Cft
21’0″ x 9″ x 9’0″ x 2 = 283.5 Cft
9’6″ x 9″ x 8’0″ x 2 = 114 . 0 Cft
20’9″ x 9″ x 8’0″x 2 = 249.00 Cft
Total = 882.75 Cft
Materials required
Cement = 36 Nos
Sand = 265 Cft
Brick = 11035 Nos
Inside all thickness is = 9 inch
8’0″ X 9″0″ X 2 = 144 Sft
4’7 1/2 ” x 3 x 8’0″ = 111 sft
4’0″ x3 x 8’0″ = 96 sft
Total = 351.00 Sft
Materials required
Cement = 8 Nos
Sand = 54 Cft
Brick = 1790 Nos
Inner wall plastering
8’0″ X 9’0″ X 8 = 576
20’9″ X 8’0″ X 2 = 332
9’6″ X 8’0″ X 2 = 152
4′ 71/2″ X 8’0″ X 6 = 222
Total = 1282
Materials required
Cement = 23 Nos
Sand = 167 Cft
External wall plastering
8’0″ x 11’0″ x 4 = 352
21’0″ x11’0″ x 2 = 462
20’9″ x 9’0″ x 2 = 373.5
9’6″ x 9’0″ x 2 = 171.00
Total = 1358.50 sft
Materials requried
Cement = 21 Nos
Sand = 177 Cft
R.C.C Roof slab
8’0″ x 21’0″ x 0.375 x 2 = 126.00 Cft
20’9″ x 9’6″ x 0.375 = 73.92 Cft
Total = 199.92 Cft
Materials required
cement = 34 nos
Sand = 130 cft
3/4 Aggregate = 169 cft
P.C.C in Flooring
8’9″ x 21’0″ x 2 = 367.5
20’9″ x 9’6″ = 197.125
Total = 564.625 Cft
Materials required
Cement = 46 Nos
Sand = 368 Cft
11/2 Aggregate = 480 Cft
Total material requirements
Cement = 212 nos x 185 = 39220
Sand = 2189 cft x 12 = 26268
Brick = 18000 x 2.40 = 43200
11/2 Aggregate = 135 cft x 20 = 2700
3/4 Jally = 462 cft x 28 = 12936
Steel required for beam, column, and slab
8 mm = 210 kg x 30 = 6300
10 mm = 112 kg x 30 = 3360
6 mm = 180 kg x 30 = 5400
Cement = 214 nos x 185 rs = 39,590 Rs
Sand = 1328 Cft x 12 Rs = 15936 Rs
Brick = 12,825 x 2.4 Rs = 30780 Rs
3/4 Aggregate = 340 Cft x 29 Rs = 9860 Rs
1 1/2 Aggregate = 526 Cft x 20 Rs = 10520 Rs
Total Cost of steel required
10 mm = 224 Kg x 30 Rs = 6720 Rs
8 mm = 450 Kg x 30 Rs = 13500 Rs
6 mm = 400 Kg x 30 Rs = 12000 Rs
Mason = L.S = 57600 Rs
Helper’s = L.S = 35800 Rs
Door’s & windows = L.S = 40000 Rs
Centering Labor = L.S = 35000 Rs
Water Tank = L.S = 12000 Rs
Plumbing Work = L.S = 20000 Rs
White washing = L.S = 30000 Rs
Total Building Project Cost = 508690 Rs/=
This is the real building project for boy modal school and the above is the total Estimation of project.