Soil nailing technique used to reinforce soil to make it more stable. Added to that, it is used for slopes, excavations, retaining walls etc. to make it more stable. They are commonly used as a remedial measure to stabilise embankments, levees, and so on. Other applications for soil nailing include:

1- Temporary excavation shoring.

2- Tunnel portals.

3- Roadway cuts.

4- Underbridge abutments.

5- Repair and reconstruction of existing retaining structures.

The main considerations for deciding whether soil nailing will be appropriate include; the ground conditions, the suitability of other systems, such as ground anchors, geosynthetic materials, and so on and cost. Although soil nails are versatile and can be used for a variety of soil types and conditions, it is preferable that the soil should be capable of standing – without supports – to a height of 1-2 m for no less than 2 days when cut vertical or near-vertical.

Soils which are particularly suited to soil nailing include clays, clayey silts, silty clays, sandy clays, glacial soils, sandy silts, sand, gravels. Soil nailing can be used on a weathered rock as long as the weathering is even (i.e. without any weakness planes) throughout the rock. Soils which are not well-suited to soil nailing include those with a high groundwater table, cohesion-less soils, soft fine-grained soils, highly-corrosive soils, loess, loose granular soils, and ground exposed to repeated freeze-thaw action.

Design considerations that will inform the design include

1- Strength limit: The limit state at which potential failure or collapse occurs.

2- Service limit: The limit state at which loss of service function occurs resulting from excessive wall deformation.

3- Height and length.

4- Vertical and horizontal spacing of the soil nails.

5- Inclination of the soil nails.

6- Ground properties.

7- Nail length, diameter and maximum force.

8- Drainage, frost penetration, external loads due to wind and hydrostatic forces.

A drainage system may be inserted once all the nails are in place. This involves a synthetic drainage mat placed vertically between the nail heads, which extends to the wall base and is connected to a footing drain.

Some of the advantages of using soil nailing include

1- They are good for confined spaces with restricted access.

2- There is the less environmental impact.

3- They are relatively quick and easy to install.

4- They use fewer materials and shoring.

5- They are flexible enough to be used on new constructions, temporary structures or on remodelling processes.

6- The height is not restricted.

Limitations and disadvantages of using soil nailing include

1- They are not suitable for areas with a high water table.

2- In soils of low shear strength, very high soil nail density may be required.

3- They are not suitable for permanent use in sensitive and expansive soils.

4- Specialist contractors are required.

5- Extensive 3D modelling may be required.